JULY 26, 2021 |
![]() |
![]() |
![]() |
Meeting Minutes - Meeting Minutes |
Present Chairman Jerome Theobald; Vice-Chairman John Haggarty; Secretary James LaPoint; Treasurer John Feik; Assistant Secretary George Firmstone; Tammy Jensen, Administrator; Dan Guinther, Plant Superintendent; Mary Peters, Engineer; Solicitor Anthony Magnotta
Absent Assistant Treasurer James Brennan
Engineer Mary Peters attended the meeting via telephone.
Visitors None
Pledge of Allegiance
Motion On a motion made by John Haggarty and seconded by George Firmstone the Board approved the meeting minutes from June 28, 2021, as presented. Motion carried. Roll Call Mr. Firmstone, Yes Mr. Feik, Yes Mr. LaPoint, Yes Mr. Haggarty, Yes Mr. Theobald, Yes Mr. Brennan, Absent
Solicitor’s Report
Letters have been forwarded to Titan Industrial Services and Integrity Fusion Products concerning the necessary warranty work to be performed. In addition, it is my understanding that we have recently received notification that a portion of SBR tanks 2 & 3 are leaking during rain situations. I have forwarded all the necessary warranty to our project engineer Mary Peters so that she may make a formal demand for warranty work to be performed by Titan with products to be supplied by Sherwin Williams.
2. Gunuskey License Agreement Tony Waldron is still waiting to hear from ReLTEK regarding the proposed right-of-way crossing for access to property.
3. Northeast Infrastructure, LLC/Robert Suhosky I have once against requested additional information from Attorney Bugaj and I’m awaiting his reply. The map supplied to the authority was a proposed map, not an As-Built plans. I shall keep the board advised.
4. White Mills Project It is my understand that Jeffery Adams, No. 241-Civil-2021, one of the Defendants has completed connection to the system.
Defendants Mary Irwin, No. 213-Civil-2021; Loretta Nardone No. 220-Civil-2021; and Corey Peterson, No. 212-Civil-2021 have not replied to the Complaint. A motion for Judgment has been filed with the Court, but has not been signed by Judge Edwards. I am currently awaiting a court date from Judge Edwards as to the hearing on the Motions for Judgment.
Defendant Jarl Thunberg No. 214-Civil-2021 has not been served. We are currently awaiting official notification from the Sheriff on this matter.
5. White Mills Restoration I will defer to Entech Engineering as to the current status of the White Mills Restoration work. It is my understanding that the work has not been completed.
Engineer’s Report
(1) Contractor: Leeward Construction, Inc (2) Dates: (a) Notice to Proceed: January 9, 2019 (b) Substantial Completion: November 20, 2020 (c) Final Completion: May 21, 2021 (3) Contract Amount: $5,193,193.00 (a) Revised Contract Amount: $5,412,931.41
(a) Payment Application #23 (Final) – $3,225.00 (Not Submitted)
(1) MHP Invoice
(1) Contractor: Pioneer Construction Co, Inc. (2) Dates: (a) Notice to Proceed: October 24, 2018 (b) Substantial Completion: February 28, 2020 (c) Final Completion: May 21, 2021 (3) Contract Amount: $2,560,969.00 (a) Revised Contract Amount: $ 2,679,409.94
(1) Payment Application #13 (Final) – $15,900 (Recommend for Approval Pending RUS Approval of Revised CO #7) (a) Actual Payment - $10,300
(1) “Certificate of Substantial Completion” - Complete/Approved (2) Final “Over/Under” adjusting Change Order – Complete/Approved (3) Certification of Contractors’ Release - Form RD 1924-9 - Not Submitted (4) Certification of Release by Claimants - Form RD 1924-10 - Not Submitted Engineer’s certification letter indicating that the project was completed in accordance with approved plans and specifications and that all Punch list items have been completed – Signed/ Need Board Approval (Pending Contractor Submissions) (5) Board Resolution indicating acceptance of the project as completed and authorizing final payment – Need Board Approval (Pending Contractor Submissions) (6) Certification of Environmental Mitigation Measures – Signed/ Need Board Approval (Pending Contractor Submissions) (7) Consent of Surety Company to Final Payment - Not Submitted (8) Builder’s Warranty Form RD 1924-19 - Not Submitted
(1) 2018 Sewer Main Replacement (2) Cliff Street Area (3) Lackawaxen River Rehabilitation Project (4) SBR Rehabilitation Project (a) Coating Issues
(1) Notice to Proceed: August 19, 2020 (2) Substantial Completion: November 2, 2020 (75 Days) (3) Final Completion: November 17, 2020 (90 Days)
(1) Payment Application #3 – Not Submitted
(1) Complete
Plant Report
Motion On a motion made by James LaPoint and seconded by John Feik the Board approved the purchase of two Barnes BLADE submersible 15HP grinder pumps from Koberlein Environmental Services in the amount of $14,362.00 plus shipping for the SBR. Motion carried. Roll Call Mr. Feik, Yes Mr. LaPoint, Yes Mr. Haggarty, Yes Mr. Theobald, Yes Mr. Brennan, Absent Mr. Firmstone, Yes
Administration Report
Motion On a motion made by James LaPoint and seconded by John Haggarty the Board approved the monthly invoices for payment as presented. Motion carried. Roll Call Mr. LaPoint, Yes Mr. Haggarty, Yes Mr. Theobald, Yes Mr. Brennan, Absent Mr. Firmstone, Yes Mr. Feik, Yes
The meeting was adjourned at 7:30 p.m. The next Board meeting is scheduled for August 23, 2021.
James LaPoint, Secretary |